A warehouse project near the Colorado River floodplain encountered over six meters of soft clay and silt. Waiting years for natural consolidation was not an option. We designed a preloading with surcharge sequence that accelerated settlement from months to weeks. Before starting, we ran a permeability field test to estimate drainage rates and an SPT program to profile the clay layers. The surcharge height reached 3.5 meters, combining fill weight with a water load to target 90% primary consolidation within 90 days. Field settlement plates confirmed the predicted curve within 12% deviation.

A staged surcharge of 3.5 meters achieved 90% primary consolidation in 90 days on Austin's soft alluvial clays.